Myth-busting Permitting, industrial policy & green stimulus: 10 misconceptions holding teams back

Myths vs. realities, backed by recent evidence and practitioner experience. Focus on interconnection queues, permitting timelines, and bankability constraints.

Despite $116 billion in 181 climate-tech manufacturing investments announced through November 2024 under the US Inflation Reduction Act, and over $1 billion allocated to improve permitting processes, persistent misconceptions continue to derail project timelines, distort investment decisions, and create unnecessary barriers to deployment (White House, 2024). This analysis dissects the ten most damaging myths about permitting, industrial policy, and green stimulus—replacing conventional wisdom with evidence from practitioners navigating these systems daily.

Why It Matters

The energy transition is increasingly constrained not by technology or capital, but by the administrative capacity to approve and interconnect projects. US interconnection queues have grown to over 2,600 GW of proposed capacity—more than double the current US generating fleet—with average wait times exceeding 5 years (Lawrence Berkeley National Laboratory, 2024). In the EU, transmission permitting timelines average 10-15 years, threatening to delay achievement of 2030 renewable targets.

For policy and compliance teams, these realities create urgent planning challenges. Projects that begin permitting today may not achieve commercial operation until the 2030s, fundamentally changing investment economics and risk profiles. Teams operating under misconceptions about permitting timelines, policy stability, or incentive availability make decisions that appear sound under false assumptions but fail when reality intervenes.

The commercial stakes are substantial. The Biden-Harris administration reported cutting median EIS (Environmental Impact Statement) completion time by 6 months—a 16% improvement—yet project developers consistently underestimate remaining timeline risk. Similarly, the January 2025 executive order pausing IRA fund disbursement caught many organizations off-guard, despite policy uncertainty being predictable given the political calendar.

Policy and compliance professionals who understand the actual dynamics of permitting, interconnection, and industrial policy can provide their organizations with realistic planning assumptions, appropriate risk mitigation strategies, and competitive advantage when navigating complex regulatory landscapes.

Key Concepts

The Permitting Taxonomy

Understanding different permitting categories is essential for realistic timeline planning:

NEPA Reviews: The National Environmental Policy Act requires federal agencies to assess environmental impacts before major actions. Categorical Exclusions (CEs) are fastest (weeks to months), Environmental Assessments (EAs) take 1-2 years, and full Environmental Impact Statements (EISs) average 4+ years.

State and Local Permitting: Land use, building permits, and state environmental reviews vary enormously by jurisdiction. Some states offer streamlined processes for priority projects while others require sequential multi-agency review.

Interconnection: Connecting to the electrical grid requires utility studies and agreements that often take 4-7 years and represent the binding constraint for many renewable projects.

Specialized Federal Permits: Wetlands (Army Corps), endangered species (Fish and Wildlife), air quality (EPA), and other permits can add years if triggered by project characteristics or location.

Industrial Policy Instruments

Modern industrial policy operates through multiple channels:

Instrument TypeUS ExampleEU ExampleTypical Timeline
Production Tax CreditsIRA Section 45YEU Innovation FundOngoing, policy-dependent
Investment Tax CreditsIRA Section 48ENational state aid2-5 years for project
Grant ProgramsDOE Title XVIIJust Transition Fund6-18 months application
Loan GuaranteesLPO ProgramsEIB Green Lending12-24 months
Domestic ContentIRA bonus creditsCBAM (partial)Varies by product
Manufacturing IncentivesAdvanced ManufacturingImportant Projects (IPCEI)Multi-year qualification

Key Metrics for Policy Tracking

MetricCurrent Value (2024-25)TrendSource
US Interconnection Queue Capacity2,600+ GWGrowingLBNL
Average Interconnection Wait5+ yearsWorseningLBNL
Median EIS Completion Time~4 yearsImprovingCEQ
IRA Climate Investment Announced$116 billionGrowingWhite House
EU Transmission Permit Time10-15 yearsStableACER
NEPA Categorical Exclusions Created10 (Forest Service)GrowingBiden Admin

The 10 Misconceptions

Myth 1: "Permitting reform will solve the deployment bottleneck"

Reality: While permitting reform is necessary, it's insufficient without simultaneous capacity building. The Biden administration allocated $165 million from IRA appropriations to support federal agencies and increased permitting workforce by 14% across 12 agencies—yet queues continue growing because project volume is increasing faster than processing capacity. The CITAP program aims to reduce transmission permitting from 4 years to 2 years, but achieving this requires sustained investment in agency staffing, not just procedural changes.

Myth 2: "Tax credits are stable and can be counted on for project economics"

Reality: Tax credit policy is inherently unstable across political cycles. The January 20, 2025 executive order pausing IRA fund disbursement demonstrated how quickly policy can shift. The transition from tech-specific credits (Sections 45/48) to tech-neutral credits (Sections 45Y/48E) on January 1, 2025, required significant compliance adaptation. Projects with 15-25 year operating lives cannot assume credit availability throughout their economic life.

Myth 3: "Domestic content requirements are straightforward to meet"

Reality: The IRA's domestic content bonus credits require that steel and iron be 100% US-manufactured, while manufactured products must meet escalating domestic cost percentages (40% for 2024, rising to 55% by 2027). Supply chain constraints mean many projects cannot qualify despite intentions. The January 2025 domestic content guidance update introduced alternative compliance pathways but also increased complexity.

Myth 4: "Environmental review is the primary cause of project delays"

Reality: While NEPA review is visible and politically contested, interconnection queue wait times now often exceed environmental review timelines. BLM approved the Dry Lake East Energy Center (200 MW solar) in approximately one year from environmental assessment initiation—fast by federal standards—yet typical interconnection studies take 4-5 years after entering the queue. Focusing exclusively on environmental permitting reform misses the grid interconnection constraint.

Myth 5: "Federal permitting reform is sufficient"

Reality: Federal permitting is only one layer. Many projects require state environmental review, local land use permits, and utility agreements that operate independently. States like Texas offer streamlined siting for renewable projects, while states like California layer state CEQA review atop federal NEPA, creating sequential delay. A project's total permitting timeline is determined by its slowest required approval.

Myth 6: "Green stimulus money flows quickly to projects"

Reality: Despite IRA passage in August 2022, significant funds remained unobligated through 2024. As of December 2024, $46 million in CEQ's IRA appropriations remained unobligated—available through September 30, 2026, but not yet deployed. DOE loan programs, while expanded, still require 12-24 month application and due diligence processes. Grant programs regularly exceed timeline estimates.

Myth 7: "The Inflation Reduction Act provides policy certainty through 2032"

Reality: While many IRA provisions nominally extend to 2032 or until emissions targets are met, administration-level implementation decisions significantly affect practical access. The February 2025 CEQ interim final rule removing NEPA regulations from the Code of Federal Regulations—developed partly with IRA funding—demonstrates how implementation can be reversed without legislative change. The 2024 election shifted implementation dramatically.

Myth 8: "Interconnection queue reform has solved the backlog"

Reality: FERC Order 2023 introduced "first-ready, first-served" cluster study processes intended to accelerate interconnection, but implementation varies by utility and region. Many projects in queue when reforms took effect remain under legacy procedures. New projects entering reformed processes still face multi-year study timelines, and the fundamental constraint—limited transmission capacity—persists regardless of process improvements.

Myth 9: "Project finance has adapted to the new incentive structure"

Reality: Many financiers remain uncertain about transferability mechanics for IRA tax credits and the implications of domestic content requirements for project risk. The direct pay election for tax-exempt entities introduced new compliance requirements that project finance structures are still absorbing. Insurance and legal costs for navigating incentive complexity have increased, partially offsetting credit value.

Myth 10: "Permitting delays affect all technologies equally"

Reality: Permitting burden varies dramatically by technology and project characteristics. Offshore wind faces extended timelines due to multiple federal agencies (BOEM, NOAA, Army Corps) and stakeholder complexity. Ground-mounted solar typically proceeds faster than wind due to lower visual and wildlife impacts. Energy storage connected to existing facilities may avoid new environmental review entirely. Battery manufacturing facilities face different permitting pathways than generation projects.

What's Working

Evidence-Based Approaches

Early and Comprehensive Site Selection: Developers who invest in upfront environmental and grid analysis consistently outperform those who begin permitting before understanding constraints. Pre-application consultation with agencies, early interconnection feasibility studies, and environmental fatal flaw analysis can eliminate unviable sites before significant capital is committed.

Phased Development Strategies: Rather than pursuing maximum project scale initially, phased approaches can achieve earlier interconnection for initial capacity while subsequent phases proceed through study processes. This generates revenue sooner and provides operational data that can inform later phase optimization.

State-Level Engagement: Given variation in state permitting environments, policy teams that engage proactively with state legislatures and regulatory commissions can shape emerging frameworks. Several states have created expedited permitting pathways for projects meeting specific criteria (job creation, community benefit, renewable energy).

Real-World Implementation Examples

Example 1: Ørsted's US Offshore Wind Approach Danish developer Ørsted built dedicated US permitting teams with deep agency relationships, investing in multi-year environmental studies before filing applications. Despite the challenging offshore wind permitting environment, Ørsted achieved approvals for South Fork Wind and Revolution Wind by treating permitting as a core competency requiring sustained investment rather than an obstacle to be minimized. Their approach includes early engagement with fishing communities, comprehensive wildlife monitoring, and phased construction strategies that address agency concerns proactively.

Example 2: NextEra Energy's Transmission Strategy NextEra Energy, the largest US renewable energy developer, has invested in transmission assets alongside generation, recognizing that interconnection constraints often determine project viability. Their 2024 announcement of $1.2 billion in transmission investments reflects a strategic decision to address the binding constraint directly rather than waiting for utility-led solutions. By developing transmission alongside generation, NextEra can better control interconnection timelines.

Example 3: AES Corporation's Colocation Model AES Corporation has pioneered co-locating battery storage and renewable generation at existing thermal power plant sites, leveraging existing interconnection rights and brownfield permitting pathways. This approach avoids lengthy interconnection queues and often qualifies for categorical exclusions from environmental review, compressing development timelines from 5+ years to 2-3 years for equivalent capacity.

What's Not Working

Persistent Failures

Underestimating Political Risk: Organizations that treated IRA provisions as guaranteed through their statutory terms were caught off-guard by the January 2025 implementation pause. Political risk assessment should be standard for any project with multi-year development timelines spanning potential administration changes.

Sequential Permitting Approaches: Projects that pursue federal, state, and local permits sequentially rather than in parallel accumulate unnecessary delay. Integrated permitting strategies that advance multiple approvals simultaneously—while more complex to manage—consistently achieve faster overall timelines.

Inadequate Community Engagement: Projects that treat community engagement as a compliance requirement rather than a strategic priority face opposition that translates to permitting delays, legal challenges, and political intervention. Early, genuine engagement with affected communities can identify and address concerns before they become obstacles.

Transmission Planning Disconnection: Renewable development continues to outpace transmission planning, creating stranded capacity that cannot reach markets. The disconnect between generation development (driven by tax credits and corporate demand) and transmission development (driven by utility planning processes with different timelines) represents a systemic failure that individual project optimization cannot solve.

Key Players

Established Leaders

  • NextEra Energy – Largest US renewable developer with integrated generation and transmission strategy; sophisticated permitting and policy teams with deep agency relationships
  • Ørsted – Leading offshore wind developer with comprehensive environmental and permitting capabilities; pioneered multi-year pre-application investment approach
  • AES Corporation – Innovative developer using brownfield and colocation strategies to accelerate timelines; significant battery storage portfolio
  • EDF Renewables – European utility with substantial US presence; extensive experience navigating cross-jurisdictional permitting complexity
  • Invenergy – Major independent developer with strong track record of successful project permitting across technologies

Emerging Startups

  • Generate Capital – Infrastructure investment firm specializing in sustainable infrastructure with innovative project finance structures
  • Longroad Energy – Developer focused on project optimization including permitting acceleration strategies
  • Scout Clean Energy – Growing developer with strong community engagement practices reducing permitting risk
  • Eolian – Transmission developer addressing the interconnection bottleneck directly
  • Talos Energy – Carbon capture developer navigating emerging regulatory frameworks

Key Investors & Funders

  • DOE Loan Programs Office – Largest federal clean energy lender with expanded authority under IRA; critical for first-of-kind projects
  • BlackRock Infrastructure – Major institutional investor in clean energy infrastructure with sophisticated policy risk assessment
  • Brookfield Renewable Partners – Leading infrastructure investor with global portfolio and long-term policy perspective
  • Goldman Sachs Renewable Power – Active acquirer and developer with integrated financing capabilities
  • Copenhagen Infrastructure Partners – Specialist renewable infrastructure fund with substantial offshore wind expertise

Action Checklist

  • Develop realistic permitting timelines based on technology-specific and jurisdiction-specific data rather than generic assumptions
  • Integrate interconnection queue analysis into site selection criteria before committing to development
  • Establish monitoring systems for policy implementation changes, not just legislative developments
  • Build political risk assessment into project finance models, including scenario analysis for adverse policy shifts
  • Pursue parallel permitting strategies advancing federal, state, and local approvals simultaneously where feasible
  • Invest in pre-application agency consultation to identify and address concerns before formal review begins
  • Develop community engagement strategies that treat local stakeholders as partners rather than obstacles
  • Consider brownfield and colocation opportunities that leverage existing interconnection and permitting advantages
  • Track domestic content supply chain developments and qualification pathways for applicable incentives
  • Maintain optionality in project structures to adapt to policy changes during development timelines

FAQ

Q: How should organizations plan around policy uncertainty when projects have 5+ year development timelines? A: Build scenario analysis into project economics from inception, modeling outcomes under favorable, baseline, and adverse policy scenarios. Structure projects to maintain optionality—for example, preserving ability to elect direct pay vs. tax equity depending on which proves more advantageous at the time of commercial operation. Diversify across policy jurisdictions where possible, recognizing that state-level policy may differ from federal. Most importantly, avoid project economics that depend on best-case policy assumptions; if a project only works under perfect policy conditions, it's not resilient to foreseeable political risk.

Q: What's the realistic timeline for a utility-scale solar project from development initiation to commercial operation? A: Assuming a greenfield site requiring interconnection study: 6-8 years is a reasonable baseline expectation. This includes 6-18 months for site control and preliminary development, 12-24 months for environmental review (EA or EIS depending on federal nexus), 4-5 years for interconnection study and agreement, and 12-18 months for construction. These timelines overlap partially but critical path typically runs through interconnection. Brownfield sites with existing interconnection or queue position can compress to 2-4 years. Distributed generation behind-the-meter can achieve 6-18 month timelines where interconnection is simpler.

Q: How has the January 2025 administration change affected ongoing project development? A: Three primary impacts: First, disbursement of unobligated IRA funds was paused pending review, affecting projects dependent on direct pay mechanisms or EPA grant programs. Second, NEPA regulatory reforms developed under the prior administration were reversed, returning environmental review to pre-IRA procedures. Third, wind energy project permits were specifically halted by executive order. Projects with approved permits and committed financing continue operation, but those in mid-permitting face uncertainty. The practical impact varies significantly by technology (solar and storage less affected than wind) and development stage (later-stage projects less exposed than early-stage).

Q: What strategies can accelerate interconnection queue timelines? A: Several approaches can help: First, pursue interconnection at substations with available capacity rather than locations requiring network upgrades—this requires detailed grid analysis before site selection. Second, consider energy-only interconnection where appropriate, avoiding the capacity component that triggers more extensive study requirements. Third, investigate cluster study processes that may achieve faster resolution than legacy sequential approaches. Fourth, explore behind-the-meter or distribution-connected configurations that avoid bulk power system queues entirely. Fifth, consider acquiring queue position from withdrawn projects where viable, though this carries counterparty and regulatory risk.

Q: How do European permitting challenges compare to US issues? A: European permitting challenges differ in character but not severity. Transmission permitting typically takes 10-15 years due to cross-border coordination requirements and extensive stakeholder processes. However, renewable generation permitting has improved in many EU jurisdictions following the REPowerEU initiative designating renewables as "overriding public interest." The EU's focus on permitting includes mandatory timelines (2 years for renewables in acceleration areas) that, if enforced, could achieve faster resolution than US processes. Cross-border infrastructure faces particular challenges from divergent national procedures. Overall, EU policy frameworks are more stable than US equivalents, reducing political risk, but administrative processes can be slower.

Sources

  • Lawrence Berkeley National Laboratory. (2024). Queued Up: Characteristics of Power Plants Seeking Transmission Interconnection.
  • White House. (2024). Fact Sheet: Biden-Harris Administration Delivers on Permitting Progress. April 30, 2024.
  • White House. (2024). Fact Sheet: Biden-Harris Administration Takes Action to Deliver More Projects More Quickly. August 29, 2024.
  • Government Accountability Office. (2025). GAO-25-107108: Inflation Reduction Act—Council on Environmental Quality's Uses and Oversight of Appropriations.
  • Federal Energy Regulatory Commission. (2024). Order No. 2023: Improvements to Generator Interconnection Procedures.
  • American Clean Power Association. (2024). IRA Implementation Status Report.
  • Baker Tilly. (2025). What's New with IRA Tax Credits in 2025.
  • Rhodium Group. (2024). Taking Stock: US Emissions Outlook Under Current Policy.